Summary: REOPENED THE PROCEEDING TO IMPOSE AN INTERIM TRAIL USE/RAIL BANKING CONDITION ON THE ABANDONMENT OF THE LINE.
SERVICE DATE – DECEMBER 30, 2002
DO
SURFACE TRANSPORTATION BOARD
DECISION AND NOTICE OF INTERIM TRAIL USE OR ABANDONMENT
STB Docket No. AB-839 (Sub-No. 1X)
KIOWA, HARDTNER AND PACIFIC RAILROAD COMPANY– ABANDONMENT EXEMPTION–IN BARBER COUNTY, KS
Decided: December 27, 2002
Kiowa, Hardtner and Pacific Railroad Company (KHP) filed a notice of exemption under 49 CFR 1152 Subpart F–Exempt Abandonments to abandon its entire 9.93-mile line of railroad between milepost 571.85 at Kiowa and milepost 581.78 at Hardtner, in Barber County, KS. Notice of the exemption was served and published in the Federal Register on October 3, 2002 (67 FR 62094). The exemption became effective on November 2, 2002.
On December 12, 2002, the V and S
Railway, Inc. (VSRI), late-filed a request for issuance of a notice of interim
trail use (NITU) for the entire line under the National Trails System Act, 16 U.S.C.
1247(d) (Trails Act) in order to negotiate with KHP for acquisition of the
right-of-way for use as a recreational trail. The October 3 notice provided that trail
use/rail banking requests had to be filed byOctober 15, 2002. In revising
its abandonment rules in Aban. and
Discon. of R. Lines andTransp. Under 49 U.S.C. 10903, 1 S.T.B. 894 (1996)
and 2 S.T.B. 311 (1997), the Board retainedthe policy of accepting filings after
the due date when good cause is shown. Because there is noindication that
VSRI’s late-filed request will prejudice any party, it will be accepted. SeeWheeling
& Lake Erie Railway Company–Abandonment Exemption–In Starke County, OH,STB
Docket No. AB-227 (Sub-No. 10X), slip op. at 1 n.1 (STB served Nov. 7,
1997).
VSRI submitted a statement indicating
its willingness to assume financial responsibility for the management of, for
any legal liability arising out of the transfer or use of (unless the user is
immune from liability, in which case it need only indemnify the railroad against
any potential liability), and for payment of any and all taxes that may be
levied or assessed against, the right-of-way, as required at 49 CFR
1152.29, and has acknowledged that the use of the right-of-way for trail
purposes is subject to future reactivation for rail service. Also on December 12,
2002, KHP advised the Board that it has not consummated the abandonment and that
it is willing to negotiate with VSRI for interim trail use. Accordingly, a NITU
will be issued.
Trail use requests may be accepted as long
as the Board retains jurisdiction over the involved right-of-way and the carrier
is willing to enter into negotiations.
See
Rail Abandonments–Supplemental Trails
Act Procedures, 4 I.C.C.2d 152, 157-581987).
Inasmuch as KHP has not consummated
the abandonment and is willing to negotiate with VSRI for the right-of-way, a
NITU will be issued with the trail use negotiation period running 180 days from
the service date of this decision or until June 28, 2003. If no agreement
is reached within 180 days, KHP may fully abandon the line. See
49 CFR 1152.29(d)(1). Use of the right-of-way for trail purposes is subject
to restoration for railroad purposes.
This decision will not significantly affect either the quality of the human environment or the conservation of energy resources.
It is ordered:
1. This proceeding is reopened.
2. Upon reconsideration, the notice served and published in the Federal Register on October 3, 2002, exempting the abandonment of the line described above is modified to the extent necessary to implement interim trail use/rail banking as set forth below, for a period of 180 days from the service date of this decision and notice (until June 28, 2003).
3. If an interim trail use/rail banking agreement is reached, it must require the trail user to assume, for the term of the agreement, full responsibility for management of, any legal liability arising out of the transfer or use of (unless the user is immune from liability, in which case it need only indemnify the railroad against any potential liability), and for the payment of any and all taxes that may be levied or assessed against, the right-of-way.
4. Interim trail use/rail banking is subject to the future restoration of rail service and to the user’s continuing to meet the financial obligations for the right-of-way.
5. If interim trail use is implemented, and subsequently the user intends to terminate trail use, it must send the Board a copy of this decision and notice and request that it be vacated on a specified date.
6. If an agreement for interim trail use/rail banking is reached by June 28, 2003, interim trail use may be implemented. If no agreement is reached by that time, KHP may fully abandon the line.
7. This decision is effective on its service date.