Summary: GRANTED CSXT'S REQUESTS TO EXTEND THE NITU NEGOTIATING PERIOD FOR THAT PORTION OF THE LINE EXTENDING BETWEEN MILEPOST OKW 333.62 AND MILEPOST OKW 334.24, AND TO EXTEND THE TIME TO EXERCISE THE ABANDONMENT AUTHORITY FOR THAT LINE SEGMENT.
SERVICE DATE - JANUARY 27, 2003
DO
SURFACE TRANSPORTATION BOARD
DECISION
STB Docket No. AB-55 (Sub-No. 586X)
CSX TRANSPORTATION, INC.–ABANDONMENT EXEMPTION–IN McMINN COUNTY, TN
Decided: January 24, 2003
A
decision and notice of interim trail use or abandonment (NITU) served on July 27,
2001 (July 2001 decision), as corrected that same day, authorized CSX
Transportation, Inc. (CSXT), to abandon a .84-mile segment of a line of railroad
known as the Athens & Tellico Branch,
The line is formally designated as
Central Region, Appalachian Division, Athens & Tellico Branch,KD
Subdivision.
CSXT stated in its extension request that it intended to allow the abandonment authority grantedfor the line segment extending between milepost OKW 333.40 and milepost OKW 333.62 to expire.
On December 19, 2002, CSXT filed a request to further extend, until August 13, 2003, the time to consummate the abandonment and to file its notice of consummation. CSXT also requests that the NITU negotiating period be extended until June 13, 2003. CSXT submits that, as indicated in the July 27 decision, its willingness to negotiate with the City for interim trail use was conditioned on the failure of its negotiations to sell a majority of the rail line for use as an industry track for continued rail purposes. CSXT states that it recently learned that the industry is no longer interested in pursuing the purchase, but that the City is still very interested in pursuing a trail.
CSXT
has shown good cause to extend the time to consummate the abandonment and to
file its notice of consummation for that portion of the line extending between
milepost OKW 333.62 and milepost OKW 334.24. Also, because CSXT has not
consummated the abandonment of this line segment and is willing to continue
trail use negotiations, the Board retains jurisdiction and the NITU negotiating
period may be extended.
See
Rail Abandonments--Supplemental Trails
Act Procedures, 4 I.C.C.2d 152, 157-58 (1987).
This decision will not significantly affect either the quality of the human environment or conservation of energy resources.
It is ordered:
1. CSXT’s requests to extend the NITU negotiating period for that portion of the line extending between milepost OKW 333.62 and milepost OKW 334.24, and to extend the time to exercise the abandonment authority for that line segment are granted.
2. The negotiating period under the NITU is extended until June 13, 2003.
3. The authority to abandon must be exercised on or before August 13, 2003.
4. This decision is effective on its service date